Why twelve months, not twelve weeks
Most incumbents start on the re-tender when the invitation to tender lands. By then the bid team has a few weeks to answer quality questions about a contract they have run for years, and they find the evidence is scattered: KPI results in monthly reports that were emailed as PDFs, explanations for bad months in someone's inbox, social value figures in a spreadsheet a former manager kept, and client praise that nobody wrote down.
The fix is boring and effective. Treat the last year of the contract as the period in which you assemble the evidence pack, not the period in which you hope the bid goes well. Twelve months gives you four things you cannot manufacture later:
- A full year of trend data under your current process. If you improved something in month 40, the buyer can only see the effect if you have a clean baseline either side of it.
- Time to close gaps. A social value commitment that is behind in month 48 can still be delivered by month 60. In month 59 it cannot.
- Fresh explanations. A miss written up the week it happened, with the job records attached, is evidence. The same miss reconstructed a year later is an excuse.
- Client sign-off. Case studies and named referees need the client's agreement, and that takes longer than a bid window allows.
This is different from monthly contract reporting. The FM contract KPI reporting guide covers the monthly scorecard the client receives. The evidence pack is what you assemble from that history to persuade a scoring panel that the next term will be better than the last.
What goes in the evidence pack
Each item below proves something specific. The "start" column is how many months before contract end to begin collecting it, so that a full set exists by the time the tender is published.
| Evidence | What it proves to a scorer | Start | Usual owner |
|---|---|---|---|
| KPI results by month, with numerator and denominator | You measured honestly and can show the arithmetic | 12 | Operations |
| Trend line per KPI over 24 months | Performance is improving, not just above target | 12 | Operations |
| Every missed month, with cause and evidence | You understand failure and act on it | 12 | Contract manager |
| Corrective actions with the month they took effect | Changes were deliberate and measured | 12 | Contract manager |
| Social value delivered against tender commitments | You keep promises made at the last bid | 12 | Bid or HR lead |
| Innovation log with a before-and-after measure | Ideas were implemented, not proposed | 12 | Operations |
| Client survey scores and comments | The people on site rate the service | 12 | Account manager |
| Compliments and complaints, with closure dates | Problems were closed, not just logged | 9 | Helpdesk |
| Asset condition and backlog at handback | You know the estate and are not hiding work | 9 | Engineering lead |
| Named referees confirmed | Someone at the client will speak for you | 6 | Account manager |
| Client-approved case studies | Specific outcomes the client agrees with | 6 | Bid lead |
| Lessons for mobilising the next term | The next term will start better than this one did | 6 | Contract manager |
The last row links to the next contract's first months. If you win, the plan you wrote here becomes the starting point for contract mobilisation reporting.
Where public sector rules come in
Three parts of the UK framework make performance evidence matter more than it used to. This is a summary; read the primary text and take advice for your own contract.
- Published KPIs. Under section 52 of the Procurement Act 2023, a contracting authority must set at least three KPIs before entering into a public contract worth more than £5 million, unless it decides performance cannot appropriately be assessed that way, and must publish them. Section 71 requires the authority to assess performance against those KPIs at least once every twelve months and on termination, and to publish information about that assessment. Which contracts are in scope is covered in our Procurement Act 2023 KPIs guide.
- Past performance as an exclusion ground. Schedule 7, paragraph 12 sets out discretionary exclusion grounds for breach of contract and poor performance, including where a supplier did not perform a contract to the authority's satisfaction, was given a proper chance to improve and did not. A well-kept record of misses and the fixes that followed is your side of that story.
- Social value commitments. For central government bodies, PPN 002 requires a minimum 10% weighting for social value and says commitments made during the procurement must be reflected in the contract, for example as KPIs. Local authorities are not named in it but many run their own social value policies, so check the buyer's.
The data model
Sources and fields
| Source | Record | Fields used |
|---|---|---|
| Job system or CAFM | Job | job ref, contract ref, site, job type (planned or reactive), priority, logged time, attended time, completed time, due date, visit count, status |
| Helpdesk | Call | call ref, job ref, site, contact, logged time, category (complaint, compliment, request), closed date |
| Survey tool | Response | job ref, site, score, comment, sent date |
| Contract schedule | KPI | KPI id, definition, numerator rule, denominator rule, target, service credit |
| Exception log | Miss | KPI id, month, actual, cause, corrective action, evidence link, author, date written |
| HR or training | Apprentice | person ref, contract ref, start date, weeks on contract |
| Finance | Spend | supplier, supplier postcode, contract ref, net amount, period |
| Social value log | Activity | commitment id, contract ref, date, quantity, unit, evidence link |
The joins
| From | To | Join key | Why it matters |
|---|---|---|---|
| Job | Contract | contract ref | Keeps other clients' work out of the figures |
| Job | KPI | job type + priority | Decides which KPI a job counts towards |
| Survey response | Job | job ref | Ties satisfaction to the work, site and month |
| Miss | KPI result | KPI id + month | Every month below target must have one row here |
| Activity, spend, apprentice | Commitment | commitment id or contract ref | Measures delivery against what the tender promised |
| Spend | Supplier | supplier postcode | Tests "local" against the buyer's own definition |
The formulas
| Measure | Formula |
|---|---|
| KPI result (month) | numerator ÷ denominator, e.g. P1 jobs attended within 4 hours ÷ P1 jobs due |
| Rolling 12-month result | Σ numerators over 12 months ÷ Σ denominators over 12 months (not the average of monthly percentages) |
| Change | latest 12-month result − prior 12-month result, in percentage points |
| Headroom | numerator − ⌈target × denominator⌉ |
| Explained rate | misses with a recorded cause ÷ all months below target |
| Evidenced rate | misses with evidence attached ÷ all months below target |
| Social value delivery | delivered ÷ committed for the same period |
| Catch-up rate | (shortfall to date + remaining commitment) ÷ months left |
Summing numerators and denominators matters. Averaging monthly percentages gives a quiet month with eight P1 calls the same weight as a busy one with thirty, and a sharp scorer will notice if your annual figure cannot be rebuilt from the monthly data.
Evidence pack · 2 November 2026
Appendix C · Contract performance · BDC-FM-0417
4 of 4 KPIs above target
for the latest 12 months.
Corrigan Moss Facilities (fictional) for Brackenfold District Council (fictional). Contract ends 31 October 2027; 24 months of results, every missed month listed.
1. KPI results, prior 12 months against latest 12 months
| KPI | Target | Prior 12m | Latest 12m | Change | 24 months |
|---|---|---|---|---|---|
| Planned maintenance completed by due date3,858 / 3,975 latest | 95% | 94.8% | 97.1% | +2.3 pts | |
| Priority 1 reactive attended within 4 hours301 / 308 latest | 95% | 94.4% | 97.7% | +3.3 pts | |
| Reactive jobs fixed on first visit2,460 / 2,972 latest | 80% | 77.8% | 82.8% | +5 pts | |
| Site contacts satisfied (post-job survey)641 / 719 latest | 85% | 85.2% | 89.2% | +4 pts |
Dashed line: contract target. Dots: months below target.
2. Months below target, and why
28 misses · 16 evidenced · 7 note only · 5 unexplained
| Month | KPI | Result | Cause recorded | Status |
|---|---|---|---|---|
| 2024-11 | PPM | 94.6% / 95 | Access refused at two sites; council keyholder unavailable | Evidence attached |
| 2024-11 | FTF | 77.6% / 80 | Parts lead time on boiler controls; supplier delay logged | Evidence attached |
| 2024-12 | PPM | 94.7% / 95 | Nothing recorded at the time | Unexplained |
| 2024-12 | P1 | 89.7% / 95 | Simultaneous P1 calls at opposite ends of the district | Evidence attached |
| 2024-12 | FTF | 77.2% / 80 | New starter still learning the sites | Note only |
| 2024-12 | SAT | 81.1% / 85 | Nothing recorded at the time | Unexplained |
| 2025-01 | PPM | 92.7% / 95 | Christmas closure: visits moved with client agreement | Evidence attached |
| 2025-01 | FTF | 76.8% / 80 | Subcontractor no-show on roof works | Evidence attached |
| 2025-02 | P1 | 89.5% / 95 | Nothing recorded at the time | Unexplained |
| 2025-02 | FTF | 76.5% / 80 | Parts lead time on boiler controls; supplier delay logged | Evidence attached |
| 2025-03 | PPM | 93.3% / 95 | Two engineers off sick in the same week | Note only |
| 2025-03 | FTF | 78.4% / 80 | Nothing recorded at the time | Unexplained |
| 2025-03 | SAT | 83% / 85 | Survey sent to an out-of-date contact list | Note only |
| 2025-04 | P1 | 93.1% / 95 | Road closure on the main route; times logged | Evidence attached |
| 2025-04 | FTF | 76.4% / 80 | Nothing recorded at the time | Unexplained |
| 2025-04 | SAT | 84.4% / 85 | Complaint about noise during school hours | Evidence attached |
| 2025-05 | P1 | 93.3% / 95 | Engineer on call also covering a vacancy | Note only |
| 2025-05 | FTF | 77.7% / 80 | New starter still learning the sites | Note only |
| 2025-06 | PPM | 92.8% / 95 | Emergency boiler replacement displaced planned visits | Evidence attached |
| 2025-06 | FTF | 78.8% / 80 | Subcontractor no-show on roof works | Evidence attached |
| 2025-07 | FTF | 78.6% / 80 | Parts lead time on boiler controls; supplier delay logged | Evidence attached |
| 2025-08 | PPM | 94.4% / 95 | Access refused at two sites; council keyholder unavailable | Evidence attached |
| 2025-08 | P1 | 92.6% / 95 | Simultaneous P1 calls at opposite ends of the district | Evidence attached |
| 2025-08 | SAT | 80.4% / 85 | Survey sent to an out-of-date contact list | Note only |
| 2025-09 | FTF | 78.1% / 80 | New starter still learning the sites | Note only |
| 2025-10 | FTF | 77% / 80 | Subcontractor no-show on roof works | Evidence attached |
| 2026-02 | P1 | 93.9% / 95 | Road closure on the main route; times logged | Evidence attached |
| 2026-08 | FTF | 79.9% / 80 | Parts lead time on boiler controls; supplier delay logged | Evidence attached |
3. Social value, latest 12 months
| Commitment | Committed | Delivered | % |
|---|---|---|---|
| Apprentice weeks on contract | 104 | 96 | 92.3 |
| Spend with suppliers in the district | £180,000 | £203,400 | 113 |
| Staff volunteering hours | 120 | 64 | 53.3 |
| School careers sessions | 6 | 6 | 100 |
4. Changes made during the term
- 2025-09Keyholder rota agreed with council estates teamPPM · measured by: Access-refused visits logged before and after
- 2025-10Van stock list for the 20 most-used boiler partsFTF · measured by: First-fix rate by job type, before and after
- 2025-11P1 calls routed to nearest engineer by postcodeP1 · measured by: Attendance times by month
- 2026-03Survey link sent from the job, not a monthly listSAT · measured by: Response count and satisfaction by month
5. Client feedback by quarter
| Quarter from | Satisfied | Compliments | Complaints |
|---|---|---|---|
| 2024-11 | 84.7% | 2 | 2 |
| 2025-02 | 84.8% | 4 | 5 |
| 2025-05 | 85.9% | 5 | 1 |
| 2025-08 | 85.3% | 2 | 1 |
| 2025-11 | 88.4% | 4 | 0 |
| 2026-02 | 89.8% | 7 | 0 |
| 2026-05 | 89% | 7 | 0 |
| 2026-08 | 89.4% | 7 | 2 |
6. Evidence checklist
5 ready · 4 partial · 3 missing
- Monthly KPI results with numerator and denominator12 months outReady
- Trend line per KPI, 24 months12 months outReady
- Every missed month explained, with evidence attached12 months outPartial
- Corrective actions and the month they took effect12 months outReady
- Social value delivered against tender commitments12 months outPartial
- Innovation log with before-and-after measure12 months outReady
- Client survey scores and verbatim comments12 months outReady
- Compliments and complaints log, with closure dates9 months outPartial
- Asset condition and backlog at handback9 months outMissing
- Named client referees confirmed6 months outMissing
- Case studies signed off by the client6 months outPartial
- Mobilisation lessons for the next term6 months outMissing
Worked example (illustrative, fictional)
Corrigan Moss Facilities, a fictional contractor, holds a five-year building maintenance contract with Brackenfold District Council, also fictional. The contract ends on 31 October 2027. On 2 November 2026 the contract manager builds the first version of the pack from 24 months of data, November 2024 to October 2026.
Priority 1 attendance, target 95% within four hours:
- Prior 12 months: 302 of 320 P1 jobs attended in time. 302 ÷ 320 = 94.4%, below target. To hit 95% they needed ⌈0.95 × 320⌉ = 304, so they were 2 jobs short.
- Latest 12 months: 301 of 308. 301 ÷ 308 = 97.7%. The threshold was ⌈0.95 × 308⌉ = 293, so headroom is 8 jobs.
- Change: 97.7 − 94.4 = +3.3 percentage points.
- Months below target: 5 in the prior year, 1 in the latest year (February 2026, 93.9%, road closure, attendance times attached).
- The innovation log shows P1 calls routed to the nearest engineer by postcode from November 2025, the first month of the stronger year. The pack can say what changed, when, and what the data did afterwards.
Exceptions across all four KPIs: 28 months fell below target in the 24-month window. 16 have evidence attached, 7 have a note only, and 5 have nothing recorded.
- Explained rate: (16 + 7) ÷ 28 = 82.1%.
- Evidenced rate: 16 ÷ 28 = 57.1%.
- All 5 unexplained misses fall between December 2024 and April 2025. With twelve months to go, the team can still pull the job records for those months and write them up properly; the 7 note-only misses need evidence attached too.
Social value, volunteering hours: 120 hours a year were committed at tender. 64 were delivered in the latest 12 months, which is 64 ÷ 120 = 53.3% and a shortfall of 56 hours.
- To finish the final year level with the commitment, the team needs (56 + 120) ÷ 12 = 14.7 hours a month, against the 5.3 a month (64 ÷ 12) they actually managed.
That catch-up figure only exists because the pack was started with a year left. In the same table, district supplier spend sits at 113% of commitment (£203,400 against £180,000), which is worth a line in the quality response.
Writing up a miss so it helps you
A scorer reading your exception log is asking whether you would handle the same failure on their contract. A good entry has five parts, all of which come from data you already hold:
- The number. The KPI, the month, the result and the target. No rounding up.
- The cause, in one line. Specific enough to check: "road closure on the main route", not "external factors".
- The evidence. Job references, attendance timestamps, a supplier delay notice, a client email agreeing to reschedule.
- What changed. The corrective action and the month it took effect.
- What the data did next. The following months' results for the same KPI.
Write it the week it happens. The person who knows why February went wrong may not be on the contract next autumn.
How to automate it with IVP.ai
The IVP.ai Data Layer pulls jobs, helpdesk calls, survey responses, spend and social value records into one governed model each night, keyed on contract ref, job ref and month. KPI results are calculated from numerators and denominators, so the 12-month figure always rebuilds from the monthly rows. A national fire safety and security company used the same approach to put HubSpot, Uptick and finance spreadsheets into one governed view, saving more than ten hours a week on reporting.
Deskless by IVP.ai can then watch the pack as it builds. When a KPI drops below target, a Deskless agent opens a row in the exception log, attaches the jobs behind the figure and asks the contract manager for a cause, rather than writing one itself. It flags social value commitments running behind their catch-up rate and lists checklist items still missing as the end date approaches. People write the explanations and decide what goes in the bid.
The KPIs themselves usually sit in a wider set of measures; the field service KPIs template lists them, and the field service reporting hub has the other templates.
To see the appendix built from your own contract data, start with the free 48-hour pilot. We connect up to three sources, such as your job system, helpdesk and finance, clean the data and set one report or agent running within 48 hours of read-only access. You then have 14 days of access to decide whether to choose a plan or walk away.