The re-tender evidence pack: start 12 months before the contract ends

A re-tender is scored on evidence, and most of the useful evidence has to be collected while the contract is still running. This guide sets out a retender evidence pack checklist, the data behind each item, and a sample performance appendix to start building twelve months before the contract ends.

By Simon DuttonLast reviewed

Why twelve months, not twelve weeks

Most incumbents start on the re-tender when the invitation to tender lands. By then the bid team has a few weeks to answer quality questions about a contract they have run for years, and they find the evidence is scattered: KPI results in monthly reports that were emailed as PDFs, explanations for bad months in someone's inbox, social value figures in a spreadsheet a former manager kept, and client praise that nobody wrote down.

The fix is boring and effective. Treat the last year of the contract as the period in which you assemble the evidence pack, not the period in which you hope the bid goes well. Twelve months gives you four things you cannot manufacture later:

  • A full year of trend data under your current process. If you improved something in month 40, the buyer can only see the effect if you have a clean baseline either side of it.
  • Time to close gaps. A social value commitment that is behind in month 48 can still be delivered by month 60. In month 59 it cannot.
  • Fresh explanations. A miss written up the week it happened, with the job records attached, is evidence. The same miss reconstructed a year later is an excuse.
  • Client sign-off. Case studies and named referees need the client's agreement, and that takes longer than a bid window allows.

This is different from monthly contract reporting. The FM contract KPI reporting guide covers the monthly scorecard the client receives. The evidence pack is what you assemble from that history to persuade a scoring panel that the next term will be better than the last.

What goes in the evidence pack

Each item below proves something specific. The "start" column is how many months before contract end to begin collecting it, so that a full set exists by the time the tender is published.

Evidence What it proves to a scorer Start Usual owner
KPI results by month, with numerator and denominator You measured honestly and can show the arithmetic 12 Operations
Trend line per KPI over 24 months Performance is improving, not just above target 12 Operations
Every missed month, with cause and evidence You understand failure and act on it 12 Contract manager
Corrective actions with the month they took effect Changes were deliberate and measured 12 Contract manager
Social value delivered against tender commitments You keep promises made at the last bid 12 Bid or HR lead
Innovation log with a before-and-after measure Ideas were implemented, not proposed 12 Operations
Client survey scores and comments The people on site rate the service 12 Account manager
Compliments and complaints, with closure dates Problems were closed, not just logged 9 Helpdesk
Asset condition and backlog at handback You know the estate and are not hiding work 9 Engineering lead
Named referees confirmed Someone at the client will speak for you 6 Account manager
Client-approved case studies Specific outcomes the client agrees with 6 Bid lead
Lessons for mobilising the next term The next term will start better than this one did 6 Contract manager

The last row links to the next contract's first months. If you win, the plan you wrote here becomes the starting point for contract mobilisation reporting.

Where public sector rules come in

Three parts of the UK framework make performance evidence matter more than it used to. This is a summary; read the primary text and take advice for your own contract.

  • Published KPIs. Under section 52 of the Procurement Act 2023, a contracting authority must set at least three KPIs before entering into a public contract worth more than £5 million, unless it decides performance cannot appropriately be assessed that way, and must publish them. Section 71 requires the authority to assess performance against those KPIs at least once every twelve months and on termination, and to publish information about that assessment. Which contracts are in scope is covered in our Procurement Act 2023 KPIs guide.
  • Past performance as an exclusion ground. Schedule 7, paragraph 12 sets out discretionary exclusion grounds for breach of contract and poor performance, including where a supplier did not perform a contract to the authority's satisfaction, was given a proper chance to improve and did not. A well-kept record of misses and the fixes that followed is your side of that story.
  • Social value commitments. For central government bodies, PPN 002 requires a minimum 10% weighting for social value and says commitments made during the procurement must be reflected in the contract, for example as KPIs. Local authorities are not named in it but many run their own social value policies, so check the buyer's.

The data model

Sources and fields

Source Record Fields used
Job system or CAFM Job job ref, contract ref, site, job type (planned or reactive), priority, logged time, attended time, completed time, due date, visit count, status
Helpdesk Call call ref, job ref, site, contact, logged time, category (complaint, compliment, request), closed date
Survey tool Response job ref, site, score, comment, sent date
Contract schedule KPI KPI id, definition, numerator rule, denominator rule, target, service credit
Exception log Miss KPI id, month, actual, cause, corrective action, evidence link, author, date written
HR or training Apprentice person ref, contract ref, start date, weeks on contract
Finance Spend supplier, supplier postcode, contract ref, net amount, period
Social value log Activity commitment id, contract ref, date, quantity, unit, evidence link

The joins

From To Join key Why it matters
Job Contract contract ref Keeps other clients' work out of the figures
Job KPI job type + priority Decides which KPI a job counts towards
Survey response Job job ref Ties satisfaction to the work, site and month
Miss KPI result KPI id + month Every month below target must have one row here
Activity, spend, apprentice Commitment commitment id or contract ref Measures delivery against what the tender promised
Spend Supplier supplier postcode Tests "local" against the buyer's own definition

The formulas

Measure Formula
KPI result (month) numerator ÷ denominator, e.g. P1 jobs attended within 4 hours ÷ P1 jobs due
Rolling 12-month result Σ numerators over 12 months ÷ Σ denominators over 12 months (not the average of monthly percentages)
Change latest 12-month result − prior 12-month result, in percentage points
Headroom numerator − ⌈target × denominator⌉
Explained rate misses with a recorded cause ÷ all months below target
Evidenced rate misses with evidence attached ÷ all months below target
Social value delivery delivered ÷ committed for the same period
Catch-up rate (shortfall to date + remaining commitment) ÷ months left

Summing numerators and denominators matters. Averaging monthly percentages gives a quiet month with eight P1 calls the same weight as a busy one with thirty, and a sharp scorer will notice if your annual figure cannot be rebuilt from the monthly data.

IVP.ai / Data Layer

Evidence pack · 2 November 2026

Appendix C · Contract performance · BDC-FM-0417

4 of 4 KPIs above target
for the latest 12 months.

Corrigan Moss Facilities (fictional) for Brackenfold District Council (fictional). Contract ends 31 October 2027; 24 months of results, every missed month listed.

1. KPI results, prior 12 months against latest 12 months

Each KPI with its target, results for November 2024 to October 2025 and November 2025 to October 2026, and a 24-month trend
KPITargetPrior 12mLatest 12mChange24 months
Planned maintenance completed by due date3,858 / 3,975 latest95%94.8%97.1%+2.3 ptsPlanned maintenance completed by due date, monthly trendMonthly results from 2024-11 to 2026-10, ranging 92.7% to 99.1%, against a 95% target shown as a dashed line.
Priority 1 reactive attended within 4 hours301 / 308 latest95%94.4%97.7%+3.3 ptsPriority 1 reactive attended within 4 hours, monthly trendMonthly results from 2024-11 to 2026-10, ranging 89.5% to 100%, against a 95% target shown as a dashed line.
Reactive jobs fixed on first visit2,460 / 2,972 latest80%77.8%82.8%+5 ptsReactive jobs fixed on first visit, monthly trendMonthly results from 2024-11 to 2026-10, ranging 76.4% to 84.3%, against a 80% target shown as a dashed line.
Site contacts satisfied (post-job survey)641 / 719 latest85%85.2%89.2%+4 ptsSite contacts satisfied (post-job survey), monthly trendMonthly results from 2024-11 to 2026-10, ranging 80.4% to 92.9%, against a 85% target shown as a dashed line.

Dashed line: contract target. Dots: months below target.

2. Months below target, and why

28 misses · 16 evidenced · 7 note only · 5 unexplained

Every month a KPI fell below target, with the result, the cause recorded and whether evidence is attached
MonthKPIResultCause recordedStatus
2024-11PPM94.6% / 95Access refused at two sites; council keyholder unavailableEvidence attached
2024-11FTF77.6% / 80Parts lead time on boiler controls; supplier delay loggedEvidence attached
2024-12PPM94.7% / 95Nothing recorded at the timeUnexplained
2024-12P189.7% / 95Simultaneous P1 calls at opposite ends of the districtEvidence attached
2024-12FTF77.2% / 80New starter still learning the sitesNote only
2024-12SAT81.1% / 85Nothing recorded at the timeUnexplained
2025-01PPM92.7% / 95Christmas closure: visits moved with client agreementEvidence attached
2025-01FTF76.8% / 80Subcontractor no-show on roof worksEvidence attached
2025-02P189.5% / 95Nothing recorded at the timeUnexplained
2025-02FTF76.5% / 80Parts lead time on boiler controls; supplier delay loggedEvidence attached
2025-03PPM93.3% / 95Two engineers off sick in the same weekNote only
2025-03FTF78.4% / 80Nothing recorded at the timeUnexplained
2025-03SAT83% / 85Survey sent to an out-of-date contact listNote only
2025-04P193.1% / 95Road closure on the main route; times loggedEvidence attached
2025-04FTF76.4% / 80Nothing recorded at the timeUnexplained
2025-04SAT84.4% / 85Complaint about noise during school hoursEvidence attached
2025-05P193.3% / 95Engineer on call also covering a vacancyNote only
2025-05FTF77.7% / 80New starter still learning the sitesNote only
2025-06PPM92.8% / 95Emergency boiler replacement displaced planned visitsEvidence attached
2025-06FTF78.8% / 80Subcontractor no-show on roof worksEvidence attached
2025-07FTF78.6% / 80Parts lead time on boiler controls; supplier delay loggedEvidence attached
2025-08PPM94.4% / 95Access refused at two sites; council keyholder unavailableEvidence attached
2025-08P192.6% / 95Simultaneous P1 calls at opposite ends of the districtEvidence attached
2025-08SAT80.4% / 85Survey sent to an out-of-date contact listNote only
2025-09FTF78.1% / 80New starter still learning the sitesNote only
2025-10FTF77% / 80Subcontractor no-show on roof worksEvidence attached
2026-02P193.9% / 95Road closure on the main route; times loggedEvidence attached
2026-08FTF79.9% / 80Parts lead time on boiler controls; supplier delay loggedEvidence attached

3. Social value, latest 12 months

Social value commitments made at tender against what was delivered
CommitmentCommittedDelivered%
Apprentice weeks on contract1049692.3
Spend with suppliers in the district£180,000£203,400113
Staff volunteering hours1206453.3
School careers sessions66100

4. Changes made during the term

  1. 2025-09Keyholder rota agreed with council estates teamPPM · measured by: Access-refused visits logged before and after
  2. 2025-10Van stock list for the 20 most-used boiler partsFTF · measured by: First-fix rate by job type, before and after
  3. 2025-11P1 calls routed to nearest engineer by postcodeP1 · measured by: Attendance times by month
  4. 2026-03Survey link sent from the job, not a monthly listSAT · measured by: Response count and satisfaction by month

5. Client feedback by quarter

Survey satisfaction, compliments and complaints for each quarter starting in the month shown
Quarter fromSatisfiedComplimentsComplaints
2024-1184.7%22
2025-0284.8%45
2025-0585.9%51
2025-0885.3%21
2025-1188.4%40
2026-0289.8%70
2026-0589%70
2026-0889.4%72

6. Evidence checklist

5 ready · 4 partial · 3 missing

  1. Monthly KPI results with numerator and denominatorReady
  2. Trend line per KPI, 24 monthsReady
  3. Every missed month explained, with evidence attachedPartial
  4. Corrective actions and the month they took effectReady
  5. Social value delivered against tender commitmentsPartial
  6. Innovation log with before-and-after measureReady
  7. Client survey scores and verbatim commentsReady
  8. Compliments and complaints log, with closure datesPartial
  9. Asset condition and backlog at handbackMissing
  10. Named client referees confirmedMissing
  11. Case studies signed off by the clientPartial
  12. Mobilisation lessons for the next termMissing

Sources: job system, helpdesk, survey tool, social value log · one row per KPI per month

Illustrative data

Illustrative, fictional data. Supplier, council, contract and every figure are invented; not customer results or a live product screenshot.

Worked example (illustrative, fictional)

Corrigan Moss Facilities, a fictional contractor, holds a five-year building maintenance contract with Brackenfold District Council, also fictional. The contract ends on 31 October 2027. On 2 November 2026 the contract manager builds the first version of the pack from 24 months of data, November 2024 to October 2026.

Priority 1 attendance, target 95% within four hours:

  • Prior 12 months: 302 of 320 P1 jobs attended in time. 302 ÷ 320 = 94.4%, below target. To hit 95% they needed ⌈0.95 × 320⌉ = 304, so they were 2 jobs short.
  • Latest 12 months: 301 of 308. 301 ÷ 308 = 97.7%. The threshold was ⌈0.95 × 308⌉ = 293, so headroom is 8 jobs.
  • Change: 97.7 − 94.4 = +3.3 percentage points.
  • Months below target: 5 in the prior year, 1 in the latest year (February 2026, 93.9%, road closure, attendance times attached).
  • The innovation log shows P1 calls routed to the nearest engineer by postcode from November 2025, the first month of the stronger year. The pack can say what changed, when, and what the data did afterwards.

Exceptions across all four KPIs: 28 months fell below target in the 24-month window. 16 have evidence attached, 7 have a note only, and 5 have nothing recorded.

  • Explained rate: (16 + 7) ÷ 28 = 82.1%.
  • Evidenced rate: 16 ÷ 28 = 57.1%.
  • All 5 unexplained misses fall between December 2024 and April 2025. With twelve months to go, the team can still pull the job records for those months and write them up properly; the 7 note-only misses need evidence attached too.

Social value, volunteering hours: 120 hours a year were committed at tender. 64 were delivered in the latest 12 months, which is 64 ÷ 120 = 53.3% and a shortfall of 56 hours.

  • To finish the final year level with the commitment, the team needs (56 + 120) ÷ 12 = 14.7 hours a month, against the 5.3 a month (64 ÷ 12) they actually managed.

That catch-up figure only exists because the pack was started with a year left. In the same table, district supplier spend sits at 113% of commitment (£203,400 against £180,000), which is worth a line in the quality response.

Writing up a miss so it helps you

A scorer reading your exception log is asking whether you would handle the same failure on their contract. A good entry has five parts, all of which come from data you already hold:

  1. The number. The KPI, the month, the result and the target. No rounding up.
  2. The cause, in one line. Specific enough to check: "road closure on the main route", not "external factors".
  3. The evidence. Job references, attendance timestamps, a supplier delay notice, a client email agreeing to reschedule.
  4. What changed. The corrective action and the month it took effect.
  5. What the data did next. The following months' results for the same KPI.

Write it the week it happens. The person who knows why February went wrong may not be on the contract next autumn.

How to automate it with IVP.ai

The IVP.ai Data Layer pulls jobs, helpdesk calls, survey responses, spend and social value records into one governed model each night, keyed on contract ref, job ref and month. KPI results are calculated from numerators and denominators, so the 12-month figure always rebuilds from the monthly rows. A national fire safety and security company used the same approach to put HubSpot, Uptick and finance spreadsheets into one governed view, saving more than ten hours a week on reporting.

Deskless by IVP.ai can then watch the pack as it builds. When a KPI drops below target, a Deskless agent opens a row in the exception log, attaches the jobs behind the figure and asks the contract manager for a cause, rather than writing one itself. It flags social value commitments running behind their catch-up rate and lists checklist items still missing as the end date approaches. People write the explanations and decide what goes in the bid.

The KPIs themselves usually sit in a wider set of measures; the field service KPIs template lists them, and the field service reporting hub has the other templates.

To see the appendix built from your own contract data, start with the free 48-hour pilot. We connect up to three sources, such as your job system, helpdesk and finance, clean the data and set one report or agent running within 48 hours of read-only access. You then have 14 days of access to decide whether to choose a plan or walk away.

Questions

Frequently asked questions

When should an incumbent start preparing for a contract re-tender?

Start collecting evidence about twelve months before the contract ends, well before the tender is published. That gives you a full year of trend data under your current process, time to close any social value shortfall, explanations for missed months written while people still remember them, and enough time to get case studies and referees agreed by the client.

What performance evidence do tender evaluators want from an incumbent?

Usually more than a list of KPIs above target. Show monthly results with the numerator and denominator, a trend over at least two years, every month you missed with its cause and the fix, social value delivered against what you promised, measured improvements, and client feedback. Check the quality questions in the buyer's tender documents for exactly what is scored.

Should we include months where we missed a KPI?

Yes. A buyer may already hold the results, and under the Procurement Act 2023 KPI performance for larger contracts is assessed and published. Leaving misses out invites the question of what else is missing. A miss with a specific cause, attached evidence, a corrective action and better results afterwards shows the panel how you manage a contract.

How do we calculate a 12-month KPI figure for a bid?

Add up the numerators for the twelve months and divide by the sum of the denominators. Don't average the twelve monthly percentages, because that gives quiet months the same weight as busy ones. Keep the monthly rows so anyone can rebuild the annual figure from them, and show the change against the previous twelve months in percentage points.

About the author

Simon Dutton

Simon has more than 10 years of experience as a data scientist, working with start-ups, SMEs, Google and the CMA.

Last reviewed 6 November 2026.