What a variance report has to explain
Every month-end ends with the same question from the board: we said profit would be X, it was Y, why? A forecast vs actual variance report answers it in one page. It lines up each forecast line against the ledger, states the gap in pounds and as a percentage, and then explains the gaps that matter in a sentence or two each.
Most teams can produce the first half. Subtracting one column from another is easy. The hard part is the explanation, and that is where spreadsheet packs tend to go wrong in three ways:
- Signs flip between lines. Revenue up is good, costs up is bad, and a pack that shows both as "+£8,000" forces the reader to work out which is which.
- Revenue gaps are explained as one number. "Revenue £26k below forecast" says nothing about whether customers bought less, bought a cheaper mix, or paid a lower price. Those three need different responses.
- Commentary covers every line or none. Either the analyst writes a paragraph about a £120 overspend on stationery, or the board pack ships with numbers and no words.
The same structure works for budget vs actual variance analysis. A budget is usually fixed at the start of the year; a forecast is re-cut during it. Many finance teams report both columns side by side, and the mechanics below apply to either.
Agree the sign convention first
Pick one rule and print it on the report: every variance is stated as its effect on profit. Positive means favourable (F), negative means adverse (A).
| Line type | Actual above forecast | Actual below forecast |
|---|---|---|
| Revenue | Favourable, positive | Adverse, negative |
| Cost | Adverse, negative | Favourable, positive |
| Profit | Favourable, positive | Adverse, negative |
So a cost variance is forecast minus actual, and a revenue variance is actual minus forecast. With that rule every column adds up: revenue variances plus cost variances equal the profit variance, which is what lets you draw a bridge at all. Percentages are variance divided by forecast, so a cost 18.5% over forecast shows as −18.5%.
The data model
Sources and fields
The report needs three inputs: the forecast, the actuals, and the drivers behind revenue. For a payments business the drivers are processed volume and take rate per product; a wholesaler would use units and price per unit; a subscription business, accounts and average revenue per account.
| Input | Typical source | Fields used |
|---|---|---|
| Forecast or budget | Xero Budgets | BudgetID, Type (OVERALL or TRACKING), BudgetLines[].AccountCode, BudgetBalances[].Period, BudgetBalances[].Amount |
| Forecast or budget | NetSuite budget import records | account, category, subsidiary, year, periodamount1 onwards |
| Forecast drivers | Forecast workbook | product, period, forecast volume, forecast take rate (bps), forecast cost rate (bps) |
| Actuals | Xero Journals | JournalDate, JournalLines[].AccountCode, JournalLines[].NetAmount, TrackingCategories |
| Actual drivers | Platform or operational database | product, period, processed volume, revenue billed |
| Report mapping | Maintained by finance | account code, report line, line type (revenue or cost), line owner |
Xero field names are from Xero's Accounting API OpenAPI specification, which also defines a /Reports/ProfitAndLoss endpoint (with fromDate, toDate, periods and timeframe parameters) and a /Reports/BudgetSummary endpoint if you would rather pull a ready-made report than journals. Oracle documents NetSuite budgets in REST web services as the budget import record, one record per account line of a budget. That page shows how budgets are created; check in your own account which read methods are available before relying on it as a source.
Driver forecasts rarely live in the accounting system. They sit in the workbook the forecast was built in, which is why the workbook has to be treated as a source with its own version, not a file someone pastes from.
The joins
| From | To | Join key | Notes |
|---|---|---|---|
| Ledger line | Report line | account code via the mapping table | One account maps to one line; many accounts can share a line |
| Forecast line | Report line | account code (or the workbook's line name, mapped once) | Pin the forecast version: the report must say which forecast it is against |
| Forecast | Actuals | report line + period (YYYY-MM) | Xero budget periods are text like "2026-10"; journal dates need converting to the same form |
| Actual drivers | Ledger revenue | product + period | A check, not a join for the figures: volume × rate should agree with the ledger before anything is split |
| Forecast drivers | Actual drivers | product code | Product codes must be the same list in both; a new product needs a zero forecast row, not a missing one |
The driver check matters. If volume × take rate does not agree with booked revenue for a product, there is an accrual, a refund or a mapping error in the way, and splitting the revenue variance on mismatched numbers produces confident nonsense.
The formulas
Revenue variance for each product splits into three parts. Here V is volume, R is the take rate, S is the product's forecast share of total volume, and f and a mean forecast and actual.
| Part | Formula | Answers |
|---|---|---|
| Volume | (total actual V × S − forecast V) × forecast R | Did the business process more or less in total? |
| Mix | (actual V − total actual V × S) × forecast R | Did the volume shift towards cheaper or dearer products? |
| Price | (actual R − forecast R) × actual V | Did each product earn a different rate? |
| Check | volume + mix + price = actual revenue − forecast revenue | Must hold to the penny |
Variable costs are flexed to actual activity in the same way:
| Part | Formula |
|---|---|
| Cost volume | −(actual V − forecast V) × forecast cost rate |
| Cost rate | −(actual cost rate − forecast cost rate) × actual V |
Fixed costs have no driver, so their variance is simply forecast minus actual. Other orderings of the revenue split exist (some put price before volume, or leave a separate joint term). None is wrong; the rule is to pick one and keep it every month, or the trend in each bar means nothing.
Reading the variance bridge chart
A variance bridge chart (also called a waterfall) starts with forecast profit on the left, adds or takes away each variance as a floating bar, and lands on actual profit on the right. Because every step uses the profit-effect sign, the bars join up without any mental arithmetic. Group the revenue bars first, then variable costs, then fixed costs, so the eye reads trading before overheads.
Month-end variance · October 2026
Forecast vs actual · Cobhurst Pay (fictional)
Operating profit came in £22,465
behind forecast.
Against the Q3 reforecast (signed off 14 Sep 2026). Each step below is stated as its effect on profit: favourable (F) adds, adverse (A) takes away.
- Forecast profit
- £10,410
- Revenue £630,400
- Actual profit
- −£12,055
- Revenue £604,562
- Revenue variance
- £25,838 A
- Volume + mix + price
- Cost variance
- £3,373 F
- Processing + fixed
Bridge: forecast to actual operating profit
Favourable Adverse Total
Bridge as a table
| Step | Group | Effect on profit | Running total |
|---|---|---|---|
| Forecast | Total | £10,410 | |
| Volume | Revenue | £27,827 F | £38,237 |
| Mix | Revenue | £39,059 A | −£822 |
| Price | Revenue | £14,606 A | −£15,428 |
| Processing: volume | Cost | £13,343 F | −£2,085 |
| Processing: rate | Cost | £7,540 A | −£9,625 |
| Staff costs | Cost | £1,430 A | −£11,055 |
| Cloud and tooling | Cost | £7,210 A | −£18,265 |
| Marketing | Cost | £6,330 F | −£11,935 |
| Other overheads | Cost | £120 A | −£12,055 |
| Actual | Total | −£12,055 |
Revenue split by product
| Product | Volume | Mix | Price |
|---|---|---|---|
| Card acquiring128 → 123 bps · share 59.8% → 54% | +£22,567 | −£51,239 | −£18,850 |
| Pay by bank32 → 32 bps · share 24.7% → 30.8% | +£2,336 | +£13,440 | £0 |
| Cross-border FX64 → 68 bps · share 15.5% → 15.2% | +£2,924 | −£1,260 | +£4,244 |
| Total | +£27,827 | −£39,059 | −£14,606 |
Volume in £ processed; price is the take rate in basis points of volume. Mix uses each product's forecast share of total volume.
Draft commentary, largest first
7 of 10 lines over threshold
- Revenue: Card acquiring£47,522 A · Draft
Card revenue £47,522 A. Volume was £37.70m against £39.94m forecast, and the take rate fell from 128 to 123 bps. Price accounts for £18,850 of the gap. Reason for the lower rate not in the data: please add.
- Revenue: Pay by bank£15,776 F · Draft
Pay by bank revenue £15,776 F on volume of £21.47m against £16.54m. Share of total volume rose from 24.7% to 30.8% while card fell from 59.8% to 54%. Each pound that moved earns 32 bps instead of 128, which is why mix is £39,059 A in total.
- Processing costs: Card acquiring£10,604 F · Draft
Card processing costs £10,604 F. Lower volume saved £18,144; the cost rate rose from 81 to 83 bps, costing £7,540. Check scheme fee notices for the month before approving.
- Cloud and tooling£7,210 A · Draft
Cloud and tooling £7,210 A (£46,210 against £39,000). Supplier-level detail needed to say whether this is one-off or recurring.
- Marketing£6,330 F · Draft
Marketing £6,330 F (£18,070 against £24,400). Underspend may be timing: confirm whether committed spend moves into November.
- Revenue: Cross-border FX£5,908 F · Draft
FX revenue £5,908 F. Volume £10.61m against £10.35m; margin 68 bps against 64. Price accounts for £4,244. Confirm whether the higher margin reflects pricing or currency pair mix.
- Processing costs: Pay by bank£4,437 A · Draft
Pay by bank processing costs £4,437 A, all from higher volume: the cost rate held at 9 bps. No action suggested.
Threshold: £5,000 or more, or 10% of forecast and at least £1,000. Lines under it get no commentary.
Deskless month-end run · log
Accounting system + Forecast workbook + Platform database
- 07:00Read October ledger actuals (accounts, closed period)10 report lines mappedSynced
- 07:01Read forecast: Q3 reforecast (signed off 14 Sep 2026)10 lines · 3 driver setsSynced
- 07:01Read processed volume by product (platform database)£69.78m across 3 productsSynced
- 07:02Check ledger revenue against volume × take rateAgree for all productsDone
- 07:03Split revenue into volume, mix and price£25,838 A in totalDone
- 07:03Flex processing costs to actual volume£5,803 FDone
- 07:04Apply materiality threshold7 of 10 lines need commentaryDone
- 07:05Draft commentary for material lines7 draftsFor review
- 07:05Publish pack to board folderOff: waits for finance approvalSkipped
Worked example (illustrative, fictional)
Cobhurst Pay is a fictional payments company with three products. This is its October 2026 report against the Q3 reforecast, the same data shown in the asset above. Total processed volume was £69.78m against a forecast of £66.83m.
| Product | Forecast volume | Actual volume | Forecast rate | Actual rate | Forecast revenue | Actual revenue |
|---|---|---|---|---|---|---|
| Card acquiring | £39.94m | £37.70m | 128 bps | 123 bps | £511,232 | £463,710 |
| Pay by bank | £16.54m | £21.47m | 32 bps | 32 bps | £52,928 | £68,704 |
| Cross-border FX | £10.35m | £10.61m | 64 bps | 68 bps | £66,240 | £72,148 |
Card acquiring, step by step:
- Forecast share of volume: £39.94m ÷ £66.83m = 59.76%.
- Actual total volume at that share: £69.78m × 59.76% = £41.70m.
- Volume: (£41,703,026 − £39,940,000) × 1.28% = £22,567 F.
- Mix: (£37,700,000 − £41,703,026) × 1.28% = £51,239 A.
- Price: (123 − 128) bps × £37.70m = £18,850 A.
- Check: £22,567 − £51,239 − £18,850 = −£47,522, which is £463,710 − £511,232.
The volume bar for card is favourable even though card volume fell. That is the method working, not a mistake: the business as a whole processed 4.4% more, and the shortfall in card shows up as mix, because payments moved from a 128 bps product to a 32 bps one.
Card processing costs (forecast 81 bps, actual 83 bps): cost volume is (£37.70m − £39.94m) × 0.81% = £18,144 F; cost rate is 2 bps × £37.70m = £7,540 A; net £10,604 F.
Across all three products and the overheads, the bridge reads:
| Step | Effect on profit |
|---|---|
| Forecast operating profit | £10,410 |
| Volume | £27,827 F |
| Mix | £39,059 A |
| Price | £14,606 A |
| Processing costs, volume | £13,343 F |
| Processing costs, rate | £7,540 A |
| Staff costs | £1,430 A |
| Cloud and tooling | £7,210 A |
| Marketing | £6,330 F |
| Other overheads | £120 A |
| Actual operating profit | −£12,055 |
Revenue is £25,838 adverse in total, costs £3,373 favourable, and profit £22,465 adverse. Mix is the largest single bar, which tells the board something a one-line revenue variance never would: the problem is product mix, not demand.
Materiality: which lines get words
Set the threshold before the numbers arrive so nobody is choosing which variances to explain. Cobhurst Pay comments on any line where the variance is £5,000 or more, or is 10% or more of forecast and at least £1,000. On that rule 7 of 10 lines need commentary. Staff costs (£1,430 A, 0.8%) and other overheads (£120 A) do not; pay by bank processing costs (£4,437 A) does, because it is 29.8% of forecast.
Good commentary names the driver, sizes it, and says what is not yet known. "Card revenue £47,522 A: take rate fell from 128 to 123 bps, price accounts for £18,850; reason for the lower rate not in the data" is useful. "Revenue was lower due to market conditions" is not.
How to automate it with IVP.ai
The IVP.ai Data Layer pulls the ledger, the pinned forecast version and the operational volumes into one governed warehouse each night, keeps the account-to-line mapping in one place, and runs the driver check before any split is calculated. The volume, mix, price and cost-flex formulas then run the same way every month, so the bridge is comparable across periods.
At month-end, a Deskless by IVP.ai agent applies the materiality rule and drafts commentary for each line over the threshold, using only what is in the numbers. Where the cause is not in the data, the draft says so and asks the line owner to add it. Drafts wait for a person in finance to edit and approve them; Deskless does not publish the pack to the board unless the business sets it up to.
The same lines feed the fintech board pack, the revenue detail sits in payments revenue by product, and the cash consequences show up in a cash flow forecast from pipeline. In the fintech forecasting case study, a London fintech centralised Salesforce, its SQL platform database, Jira, its accounting platform and Segment, and forecasts that took months now take minutes. More templates are on the financial services reporting hub.
To see a variance bridge on your own numbers, start with the free 48-hour pilot. We connect up to three sources, typically the accounts, the forecast workbook and your platform database, clean the data and set one report or agent running within 48 hours of read-only access. You then have 14 days of access to choose a plan or walk away.