Why the first 90 days need their own report
A new facilities or maintenance contract rarely starts clean. The outgoing contractor hands over an asset register of uncertain quality, a list of open jobs, a set of certificates with gaps in it, and a group of people who worked for someone else last Friday. The client expects normal service from Monday, and the steady-state KPIs in the contract usually start counting on day one too.
Mobilisation reporting is the weekly record of how fast you are turning that inheritance into a contract you control. It is different from the monthly performance pack you will run for the next five years. The monthly pack asks "are we hitting the service levels?" The mobilisation report asks "how much of what we were handed have we checked, fixed or cleared, and how much is still unknown?" Without it, the first few months of KPI failures get blamed on the new contractor, when most of them were inherited.
The report rests on one discipline: write down the day-one position before anyone starts fixing things. If you don't, there is no baseline to measure progress from, and no record of what was already wrong when you arrived.
Capture the baseline on day one
Four measures do most of the work. Each needs a number and a source, frozen on the first morning of the contract.
| Baseline measure | What to count | Usual source |
|---|---|---|
| Asset register completeness | Register lines handed over; lines with location, asset type, maintenance schedule and last service date all filled | Outgoing contractor's register or the client's CAFM export |
| Transferred staff | Staff named on the employee liability information; staff who actually transferred | Outgoing employer, then your HR system |
| Inherited backlog | Open reactive jobs; planned tasks already overdue | Outgoing helpdesk export, client's job list |
| Statutory items found overdue | Inspections, tests and examinations past their due date, by site and item | Certificates and logbooks handed over, then your own site surveys |
Staff numbers are the one measure you should already have before day one. Under regulation 11 of the TUPE Regulations 2006, the outgoing employer must give the incoming one employee liability information about the transferring staff. In England, Wales and Scotland the notice period has been at least 28 days before the transfer since a 2014 amendment, unless special circumstances make that impractical. Counting from that list means onboarding is measured against the people you were told were coming, and the gap between "named" and "turned up" is visible.
The statutory count is the measure most likely to grow after day one. Handover records only show what the previous contractor knew. Site surveys find plant that was never on the schedule: a passenger lift nobody booked for its thorough examination, a pressure vessel without a written scheme. HSE's guidance on thorough examination of lifting equipment sets default intervals of six months for equipment that lifts people and twelve months for most other lifting equipment, unless a competent person's examination scheme says otherwise. That is the kind of date you are checking each item against. Log each item as a separate row with the date it was found and how it was found, so items from handover records and items found on survey can be reported separately.
The data model
A mobilisation report pulls from at least four places: the handed-over register, your own CAFM or job system, the HR or workforce system, and the certificate store. None of them was set up for this report, so the joins are worth writing down.
Fields
| Source | Record | Fields used |
|---|---|---|
| Handover pack | Asset register line | asset ID, site, asset type, location, maintenance schedule, last service date |
| Your CAFM or job system | Asset | asset ID, site, verified date, verified by, disposed flag, created-on-survey flag |
| Your CAFM or job system | Job | job ref, inherited flag, original job ref, status, completed date, closure reason |
| Your CAFM or job system | Planned task | task ID, asset ID, due date, completed date, inherited flag |
| HR or workforce system | Employee | employee ID, transfer date, induction date, competence records checked date, device issued date |
| Certificate store | Statutory item | item ID, site, asset ID, item type, found date, source, cleared date, certificate reference |
Joins
| From | To | Key | Watch for |
|---|---|---|---|
| Handover register line | Your asset | old asset ID, held as an alternate reference | Outgoing IDs reused for different assets on different sites |
| Inherited job | Your job | original job ref | Duplicates raised by the client and the old helpdesk for the same fault |
| Statutory item | Your asset | asset ID | Items found on survey before the asset itself is on the register |
| Employee | ELI list | name and date of birth, then your employee ID | Staff who leave before day one still sit on the ELI list |
Formulas
| Measure | Formula |
|---|---|
| Assets confirmed on site | register lines handed over − lines found disposed + assets found not on the register |
| Register complete | records with all mandatory fields ÷ assets confirmed on site |
| Onboarded | transferred staff with induction, competence check and device all dated ÷ staff who transferred |
| Backlog remaining | last week's remaining + inherited jobs found late − completed − closed by agreement |
| Backlog plan | opening backlog × (1 − week ÷ target week) |
| Statutory days open | cleared date, or report date if still open, − found date |
| New-contract PPM on time | planned tasks completed by due date ÷ planned tasks due, excluding inherited overdue tasks |
| Weeks to clear | backlog remaining ÷ average cleared per week over the last four weeks |
Two of these trip people up. The register denominator moves: every disposed asset found shrinks it and every unlisted one grows it, so the percentage can fall in a week when the team did good work. Report the denominator next to the percentage. And inherited overdue planned tasks belong in the backlog, not in the new-contract PPM figure; mixing them makes week one look like a failure you did not cause and hides whether your own schedule is running.
What goes on the weekly page
Keep it to one page with three parts: a status table comparing each measure with the day-one figure and the mobilisation plan target, a burn-down of the inherited backlog against a straight line to zero, and an exception list of statutory items either still open or cleared outside the target time. The weekly table underneath gives the trend.
The emphasis shifts through the period. Weeks 1 to 4 are about people and safety: onboarding and statutory items. Weeks 5 to 9 are about the survey and the backlog. By weeks 10 to 13 the question is whether the steady-state KPIs can safely start carrying financial weight. That matters most where the contract defers service credits until mobilisation is signed off.
Week 13 · w/e 1 Nov
Mobilisation report · Tarrowby District Council (fictional)
1 of 5 mobilisation targets met
at the end of week 13.
Total FM, 14 sites, started 3 Aug. Every measure is shown against the day-one baseline taken from the outgoing contractor’s handover.
| Measure | Day one | Week 13 | Target | Status |
|---|---|---|---|---|
| Asset register complete | 63.9% | 97.2% | 95% by week 12 | MetWeek 12: 95.5% |
| Transferred staff onboarded | 0/35 | 35/35 | All by week 4 | MissedAll by week 6 |
| Inherited backlog open | 508 | 26 | Zero by week 13 | Missed0.7 weeks at current rate |
| Statutory items cleared ≤ 28 days | 23 overdue | 33/40 | Each within 28 days | Missed1 still open |
| New-contract PPM on time | – | 91.4% | 95% from start | MissedWeek 13: 98.9% |
Inherited backlog against plan
— Actual · - - Plan to zero by week 13
Opening 508 + 43 found late − 463 completed − 62 closed by agreement = 26 open. At the last four weeks’ rate of 38 a week, that is 0.7 weeks more.
Week by week
| Wk | Register | Onboarded | Backlog | Statutory open | PPM on time |
|---|---|---|---|---|---|
| 1 | 65.2% | 9/35 | 483 / 469 | 25 | – |
| 2 | 67.6% | 21/35 | 464 / 430 | 17 | 82.9% |
| 3 | 70.3% | 29/35 | 426 / 391 | 12 | 83.9% |
| 4 | 72.9% | 33/35 | 388 / 352 | 11 | 85.5% |
| 5 | 75.6% | 34/35 | 346 / 313 | 8 | 87.3% |
| 6 | 78.6% | 35/35 | 302 / 274 | 5 | 88.4% |
| 7 | 81.6% | 35/35 | 263 / 234 | 3 | 90.4% |
| 8 | 84.6% | 35/35 | 222 / 195 | 2 | 91.4% |
| 9 | 87.5% | 35/35 | 178 / 156 | 0 | 93.4% |
| 10 | 90.5% | 35/35 | 142 / 117 | 1 | 94.7% |
| 11 | 93.2% | 35/35 | 98 / 78 | 2 | 96.6% |
| 12 | 95.5% | 35/35 | 64 / 39 | 2 | 98.8% |
| 13 | 97.2% | 35/35 | 26 / 0 | 1 | 98.9% |
Backlog shows actual / plan; amber where behind plan. Register is complete records ÷ assets confirmed on site.
Statutory items outside 28 days, or still open
41 found · 40 cleared · median 16 days
- ST-008Pressure systems examination · Westgate Day CentreHandover records · 3 Aug45 days
- ST-019Gas safety check · Cresswick Leisure CentreHandover records · 3 Aug43 days
- ST-014Fixed wiring inspection (EICR) · Tarrowby MuseumHandover records · 3 Aug38 days
- ST-020Legionella risk assessment review · Kingsmoor OfficesHandover records · 3 Aug35 days
- ST-031Pressure systems examination · North Tarrowby LibrarySite survey · 17 Aug34 days
- ST-021Fire alarm service · Hanbury Road LibraryHandover records · 3 Aug33 days
- ST-006Fixed wiring inspection (EICR) · Hanbury Road LibraryHandover records · 3 Aug31 days
- ST-041LOLER thorough examination · North Tarrowby LibrarySite survey · 21 OctOpen 12d
Worked example (illustrative, fictional)
Ostley Brook Facilities, a fictional contractor, starts a total FM contract for the fictional Tarrowby District Council across 14 sites on Monday 3 August 2026. The mobilisation plan targets are: 95% register completeness by week 12, all transferred staff onboarded by week 4, the inherited backlog cleared by week 13, every statutory item cleared within 28 days of being found, and 95% of new-contract planned tasks done on time. The report runs on Monday 2 November 2026, covering week 13.
Day one. The register has 1,862 lines, of which 1,190 have all four mandatory fields: 1,190 ÷ 1,862 = 63.9%. The ELI list names 38 people; 35 transfer. The backlog is 412 open reactive jobs plus 96 overdue planned tasks = 508. Handover records show 23 statutory items overdue.
Asset register. By week 13 the survey has found 74 listed assets that no longer exist and 131 on site that were never listed. Assets confirmed on site = 1,862 − 74 + 131 = 1,919. Complete records are 1,865, so 1,865 ÷ 1,919 = 97.2%. The target test is week 12, when the figure was 1,830 ÷ 1,916 = 95.5%: met.
Onboarding. At week 4, 33 of 35 transferred staff are fully onboarded: 33 ÷ 35 = 94.3%, so the target is missed. The last two finish in week 6.
Inherited backlog. The old helpdesk inbox turns up 23, 14 and 6 more inherited jobs in weeks 2, 3 and 4: 43 in total. Over 13 weeks the team completes 463 and closes 62 with the client's agreement as duplicates or no longer needed. Remaining = 508 + 43 − 463 − 62 = 26, against a plan of zero: missed. The last four weeks cleared 36 + 44 + 34 + 38 = 152, an average of 38 a week, so 26 ÷ 38 = 0.7 weeks more at that rate. The late finds explain the miss: at week 4 the backlog stood at 388 against a plan of 352.
Statutory items. Surveys add 18 items to the 23 from handover: 41 in total. Forty are cleared by the report date; 33 of those within 28 days, which is 33 ÷ 40 = 82.5%. The seven outside target were all found in the first three weeks, six of them from handover records. One item, a lifting equipment examination found on 21 October, is still open after 12 days, inside target. The median time to clear is 16 days.
New-contract PPM. From week 2 to week 13, 928 planned tasks fall due and 848 are done on time: 848 ÷ 928 = 91.4%, below the 95% target. Week 13 alone is 86 ÷ 87 = 98.9%.
So one of five targets is met. Read on its own that looks poor. Read against the baseline, it shows a contract that started with a third of its register incomplete and 23 statutory items overdue, and is now at 97.2%, one open item and under a week of backlog left. That is the case the contractor takes into the month-three review, and it is only possible because day one was written down.
How this connects to the contract's KPIs
For larger public contracts the mobilisation numbers feed straight into published performance. Under section 52 of the Procurement Act 2023, a contracting authority must set and publish at least three KPIs for a public contract with an estimated value over £5 million, unless it considers performance can't appropriately be assessed that way. Section 71 then requires performance against those KPIs to be assessed at least once in every twelve months and on termination, with information about each assessment published. A poor first quarter can therefore end up in the public record. What the Act requires in detail is covered in our Procurement Act 2023 KPIs guide, and the KPIs buyers typically write into FM contracts are in FM contract KPI reporting.
Once mobilisation closes, the weekly page should hand over to the monthly report. The monthly maintenance report template and the field service KPIs template are the natural next steps, and the baseline figures stay useful as the "before" column for the first annual review.
How to automate it with IVP.ai
Most mobilisation reports are built by hand in a spreadsheet, because the data sits in a handover pack, a new CAFM system that is still being loaded, an HR system and a shared drive of certificates. That is exactly when nobody has the time.
The IVP.ai Data Layer can take the handover register and outgoing helpdesk export as Excel files, read your job system and HR system through their APIs or databases, and keep the alternate references that join old asset IDs and job refs to new ones. It freezes the day-one baseline as its own snapshot so later corrections don't rewrite it. A Deskless by IVP.ai report or agent can then build the weekly page each Monday, list statutory items approaching the 28-day mark for the compliance lead, and flag inherited jobs found late for a person to confirm before they are added to the backlog. It flags and drafts; whether a job is closed by agreement with the client stays a human decision.
The same approach let a national fire safety and security company bring HubSpot, Uptick and finance spreadsheets into one governed view and save more than 10 hours a week on reporting, described in single source of truth for data. More reporting templates are on the field service reporting hub.
The workbook above is a free download with the sample rows filled in. To see the weekly page built from your own systems, start with the free 48-hour pilot: we connect up to three sources, such as your job system, HR system and the handover register, clean the data and set one report or agent running on it within 48 hours of read-only access. You then have 14 days of access to choose a plan or walk away.