Procurement Act 2023: the KPIs suppliers on larger contracts now report

Under the Procurement Act 2023, public buyers must set, assess and publish KPIs on contracts worth more than £5 million, and the rating they publish is about you. This guide sets out what the Act requires and how a supplier can calculate the same ratings from its own data before the contract performance notice goes out.

By Simon DuttonLast reviewed

Who sets, measures and publishes the KPIs

The Procurement Act 2023 does not make suppliers publish anything about their own performance. It puts the duty on the buyer. Before a contracting authority enters into a public contract with an estimated value of more than £5 million, it must set at least three key performance indicators and publish them (section 52). During the contract it must assess the supplier against them at least once in every 12-month period and on termination, and publish the result (section 71).

So why should a supplier care? Because the published rating is about you, it sits on a public platform for every other buyer to read, and it is calculated from records that mostly live in your systems: job logs, attendance times, certificates, quotes. If your own figures and the authority's assessment disagree, you want to know before the notice goes out, not after. This guide covers what the rules say, then how to rebuild the same ratings from your own data. Choosing a good KPI set for a tender is a different job, covered in FM contract KPI reporting.

What the Act and regulations require

The table below summarises the duties as they read on 5 November 2026. It is a summary, not legal advice; check the primary sources linked and your contract.

Requirement What it says Source
Which contracts Public contracts with an estimated value over £5 million s52(1)
How many KPIs At least three, set before the contract is entered into s52(1)
What a KPI is A factor or measure against which a supplier's performance can be assessed during the contract's life-cycle s52(4)
Publishing the KPIs The authority must publish any KPIs it sets; the contract details notice lists the three most material at the time s52(3); KPI guidance
Not covered Frameworks themselves (call-offs over £5 million are covered), private utilities' utilities contracts, concession contracts, light touch contracts s52(6)
Opt-out Where the authority considers performance could not appropriately be assessed by KPIs, such as a one-off delivery s52(2)
How often assessed At least once in every 12 months and on termination; more often is allowed s71(1)–(2)
Where published A contract performance notice on the central digital platform Notice guidance
What the notice shows The three KPIs the authority regards as most material at publication, a rating for each, and the period covered Regulation 39, per the notice guidance
Old-regime contracts KPI duties only apply to contracts awarded under the Act Transitional guidance

Two details matter more than they look. First, the notice reports only three KPIs, and the authority chooses which three at the time it publishes. They can differ from the three in the contract details notice and from the last notice. A supplier with eight KPIs in the schedule has to be ready on all eight. Second, the ratings are fixed by regulation: Good, Approaching target, Requires improvement, Inadequate, and Other for cases that fit none of them (no data for the period, for example). Authorities may keep their own internal scales, but the notice uses these five.

The Act sets the rating names, not the percentages behind them. "Approaching target" for a 95% attendance KPI might mean 92% in one contract and 90% in another. If your contract's KPI schedule does not define the bands, that is the first thing to agree with the authority, in writing.

A separate duty in section 71(5) covers breaches and poor performance: where a breach leads to termination of part of the contract, damages or a settlement, or where a supplier has been given a proper chance to improve and has not, the authority must publish a notice within 30 days. That is a different trigger from the routine KPI assessment, and outside the scope of the tracker below. The guidance notes that a supplier can ask for information to be withheld as commercially sensitive, but sets a high bar for doing so.

Why run the numbers yourself

The authority's assessment is only as good as the data it is given. On most service contracts that data is the supplier's monthly report, so the supplier is already doing the counting. The risk is not that the authority invents a rating; it is that a definition drifts. Your team counts emergency attendance from arrival on site, the contract counts from when the call was logged. Your certificate KPI excludes assets handed over mid-month, the authority's does not. Each mismatch is small until it moves a KPI across a band boundary in a public notice.

Running the same calculation the authority will run, on the same period, gives you three things: the rating you expect, how many successes you are from the next band up or down, and early warning when a KPI rated Good for the year is sliding in recent months. That last point matters because the guidance links these notices to the discretionary exclusion ground for poor performance in Schedule 7 to the Act, and published notices are also likely to come up when the contract is retendered. The retender evidence pack guide covers assembling that record.

The data model

Fields you need

Source Record Fields used
Contract KPI schedule KPI id, name, numerator definition, denominator definition, target, approaching-target floor, inadequate floor, measurement period
Contract Site and asset schedule site id, asset id, date added, date removed
Job system PPM task task id, site id, asset id, due date, completed date
Job system Reactive job job ref, site id, priority, logged at, attended at, closed at, return visit flag
Job system Quote quote ref, linked job ref, defect date, issued date
Compliance register Certificate asset id, certificate type, issue date, expiry date
Authority Contract performance notice publication date, period, KPI as published, rating

The joins

From To Join key Why
Job, task, certificate Site and asset schedule site id, asset id Only count work inside the contract's scope on the date it happened
Reactive job Quote job ref Ties a remedial quote to the defect that triggered it
Each record KPI schedule job type or priority mapped to KPI id One rule decides which KPI a record counts towards
Month Assessment period month between period start and end The period must match the one the authority will report
Your rating Published notice KPI and period Shows where your figure and theirs differ

The formulas

Measure Formula
Result Σ met ÷ Σ measured over the whole period
Rating Good if result ≥ target; Approaching target if ≥ approaching floor; Requires improvement if ≥ inadequate floor; otherwise Inadequate
Needed for target smallest whole number ≥ target × Σ measured
Gap Σ met − needed (negative means short)
Recent trend the same result and rating over the last three months of the period

Pool the counts; do not average twelve monthly percentages. A month with 26 emergency calls should not weigh the same as a month with 42. Where a KPI is a state rather than an event, such as certificates in date, count it at each month end and sum the certificate-months.

IVP.ai / Data Layer

Run 5 November 2026

Supplier KPI tracker · TDC-FM-2025-014

2 of 5 published KPIs at Good
for the year to 30 September 2026.

Corriebank Facilities Ltd self-assessment for Tallowmoor District Council, using the five ratings a contract performance notice uses. 9,710 counted items (jobs, tasks, quotes and certificate-months) behind the figures.

Good for the year
2 of 5
Meets or beats target
Below target
3
2 approaching · 1 requires improvement
Closest miss
2 short
KPI-5 Quotes in 10 days
Good but slipping
1
Year Good, last 3 months not

Year result against each KPI

Each KPI with counted successes over the measured total, result, contract target, rating, gap to target and rating for the last three months
KPIMet / totalResultTargetYear ratingTo targetLast 3 months
KPI-1Planned maintenance completed by due date2,401 / 2,51795.4%95%Good9 spareApproaching target 94.9%
KPI-2Emergency call-outs attended within 4 hours347 / 36994.0%95%Approaching target4 shortApproaching target 93.4%
KPI-3Statutory compliance certificates in date4,694 / 4,81097.6%100%Requires improvement116 shortRequires improvement 96.9%
KPI-4Reactive jobs fixed on first visit1,475 / 1,67588.1%85%Good51 spareGood 88.8%
KPI-5Remedial quotes issued within 10 working days304 / 33989.7%90%Approaching target2 shortGood 92.7%

Result = successes ÷ total for the whole period, not an average of monthly percentages. “To target” = successes − the smallest whole number that reaches the target. Certificates are counted once per month end, so totals are certificate-months.

Monthly result against target

  • PPM on timetarget 95%

    Planned maintenance completed by due date, monthly, October 2025 to September 2026Monthly results ranged from 93.0% to 97.1%; 4 of 12 months were below the 95% target.

    Oct 2593.0–97.1%Sep 26

  • Emergency 4htarget 95%

    Emergency call-outs attended within 4 hours, monthly, October 2025 to September 2026Monthly results ranged from 89.2% to 100.0%; 6 of 12 months were below the 95% target.

    Oct 2589.2–100.0%Sep 26

  • Certs in datetarget 100%

    Statutory compliance certificates in date, monthly, October 2025 to September 2026Monthly results ranged from 95.8% to 99.0%; 12 of 12 months were below the 100% target.

    Oct 2595.8–99.0%Sep 26

  • First-time fixtarget 85%

    Reactive jobs fixed on first visit, monthly, October 2025 to September 2026Monthly results ranged from 83.3% to 93.1%; 2 of 12 months were below the 85% target.

    Oct 2583.3–93.1%Sep 26

  • Quotes in 10 daystarget 90%

    Remedial quotes issued within 10 working days, monthly, October 2025 to September 2026Monthly results ranged from 78.8% to 96.8%; 8 of 12 months were below the 90% target.

    Oct 2578.8–96.8%Sep 26

Green bars meet the target that month; gold bars fall short. Dashed line is the target. Each chart’s vertical scale runs from 12 points below target to 100%.

Rating bands in this (fictional) contract’s KPI schedule

Contract-defined result bands mapped to the five contract performance notice ratings
KPIGoodApproaching targetRequires improvementInadequate
KPI-1≥ 95%≥ 92%≥ 85%< 85%
KPI-2≥ 95%≥ 92%≥ 85%< 85%
KPI-3≥ 100%≥ 98%≥ 95%< 95%
KPI-4≥ 85%≥ 80%≥ 70%< 70%
KPI-5≥ 90%≥ 85%≥ 75%< 75%

The rating names come from the Procurement Regulations 2024; the percentage bands do not. They are whatever the contract says. “Other” is used where no rating fits, for example no data for the period.

Hard FM and statutory maintenance, 38 civic and community buildings · from 1 October 2025

Illustrative data

Illustrative, fictional data. Supplier, authority, contract and figures are invented; not customer results, legal advice or a live product screenshot.

Worked example (illustrative, fictional)

Corriebank Facilities Ltd holds a fictional five-year hard FM contract, TDC-FM-2025-014, with the equally fictional Tallowmoor District Council: 38 civic buildings, an estimated value of £7.2 million, starting 1 October 2025. The contract has five KPIs. Corriebank runs its tracker on 5 November 2026 for the year 1 October 2025 to 30 September 2026.

KPI Met / measured Result Target Rating Gap
KPI-1 PPM on time 2,401 / 2,517 95.4% 95% Good 9 spare
KPI-2 Emergency within 4 hours 347 / 369 94.0% 95% Approaching target 4 short
KPI-3 Certificates in date 4,694 / 4,810 97.6% 100% Requires improvement 116 short
KPI-4 First-time fix 1,475 / 1,675 88.1% 85% Good 51 spare
KPI-5 Quotes in 10 working days 304 / 339 89.7% 90% Approaching target 2 short

Taking KPI-2 end to end. Over twelve months 369 emergency jobs were logged and 22 were attended outside four hours, so 347 were met. 347 ÷ 369 = 94.04%. Reaching 95% would have needed 0.95 × 369 = 350.55, rounded up to 351 attendances, so Corriebank is 4 short. The contract's approaching-target floor is 92%: 0.92 × 369 = 339.48, so 340 is needed and Corriebank is 7 clear of dropping to Requires improvement. Averaging the twelve monthly percentages instead gives 94.51%, which would hide part of the shortfall in the busier months.

KPI-3 shows how unforgiving a 100% target is. 4,694 of 4,810 certificate-months were in date, 97.59%. The contract puts Approaching target at 98%, which needs 4,714 (0.98 × 4,810 = 4,713.8, rounded up), so Corriebank is 20 certificate-months from the next band up.

KPI-1 is Good for the year with 9 to spare (0.95 × 2,517 = 2,391.15, so 2,392 needed). But the last three months, July to September, came in at 580 of 611, or 94.93%: one task short of the 581 needed for 95%. If Tallowmoor picked KPI-1, KPI-2 and KPI-3 as the most material, the notice would read Good, Approaching target and Requires improvement. If the next assessment covered a quarter rather than a year, KPI-1 could drop a band on one late task.

Every figure here is invented for illustration. The same rows are pre-filled in the tracker workbook.

A routine before each assessment

  1. Confirm the definitions. Read the KPI schedule clause by clause against how your systems timestamp events. Write down the agreed start and stop points for every time-based KPI.
  2. Fix the period. Ask the authority which period the next notice will cover and run your tracker for exactly that window.
  3. Reconcile the scope. Check sites and assets added or removed during the period against the contract schedule.
  4. Share the workings. Send the counts, not just percentages, with the monthly report so the authority's assessment starts from the same numbers.
  5. Log the notice. When the notice is published, record each rating next to yours and raise any difference straight away.

How to automate it with IVP.ai

The IVP.ai Data Layer pulls jobs, PPM tasks, quotes and certificate records from your job system and compliance spreadsheets every night, maps each record to a KPI using the contract schedule, and keeps the site and asset scope dated so a building handed back in March stops counting from March. The calculations above then run on governed data rather than a monthly export. A national fire safety and security company used the same approach to bring HubSpot, Uptick and finance spreadsheets into one governed view, saving more than 10 hours a week on reporting.

A Deskless by IVP.ai report or agent can then check each KPI weekly, flag any that are within a few successes of a band boundary, and draft the evidence pack for the next assessment for a contract manager to review. It doesn't send anything to the authority unless you configure it to. For the wider metric set behind these KPIs, see the field service KPIs template, the monthly maintenance report template and the field service reporting hub.

To see your own contract KPIs calculated this way, start with the free 48-hour pilot. We connect up to three sources, clean the data and set one report or agent running on real data within 48 hours of read-only access, with 14 days of access before you choose a plan or walk away.

Questions

Frequently asked questions

Which contracts need KPIs under the Procurement Act 2023?

Section 52 applies to public contracts with an estimated value of more than £5 million. The authority must set at least three KPIs before entering into the contract and publish them. Frameworks themselves, concession contracts, light touch contracts and utilities contracts awarded by private utilities are excluded, though call-off contracts over £5 million are covered. An authority can also decide performance cannot appropriately be measured by KPIs, for example a one-off delivery.

How often are supplier KPIs assessed and published?

Section 71 requires the authority to assess performance against the KPIs at least once in every 12-month period of the contract and on termination, and publish the result in a contract performance notice. It can assess more often if it chooses. Each notice reports the three KPIs the authority regards as most material at that time, with a rating for each and the period the assessment covers.

What ratings appear in a contract performance notice?

The Procurement Regulations 2024 set five: Good, Approaching target, Requires improvement, Inadequate and Other. Other covers cases that fit none of the four, such as no data recorded for the period. The regulations fix the names, not the percentages, so the band boundaries for each KPI depend on what the contract says or what the authority and supplier agree.

Do the KPI rules apply to contracts awarded before the Act?

No. The Cabinet Office transitional guidance says the Act's KPI obligations only apply to contracts awarded under the Act. Contracts awarded under the old regime, such as the Public Contracts Regulations 2015, continue to be managed under that legislation until they end, including valid extensions. Suppliers may still be asked for KPI reporting under the contract's own terms.

Can a supplier stop poor KPI results being published?

Not as a rule. A supplier can ask for information to be withheld as sensitive commercial information, but the authority applies a public interest test, and the Cabinet Office guidance describes a high bar because publication is generally in the public interest. The practical defence is accurate data: agree definitions early, share counts with each report, and check your own ratings before each assessment.

Sources

About the author

Simon Dutton

Simon has more than 10 years of experience as a data scientist, working with start-ups, SMEs, Google and the CMA.

Last reviewed 6 November 2026.

Your first report or agent in 48 hours.

Tell us which systems feed it. We connect them, clean the data and set the report running automatically. If it isn’t useful, walk away.